Which of the following is one of Dr. Eli Goldratt's rules of production scheduling for optimized production technology?

Which of the following is one of Dr. Eli Goldratt's rules of production scheduling for optimized production technology? 





A. If you lose an hour at a bottleneck, it is better than making scrap.

B. Do not balance capacity, balance the flow.

C. Do not allow bottlenecks to govern the flow of the line.

D. An hour saved at a bottleneck operation is a mirage.

E. The amount in a process batch should be fixed when the batch is begun and not changed over time or along its route.



Answer: B